2. CODIFICATION PROCEDURES:

2.2. FINANCIAL ASPECTS:

2.2.2. MANUFACTURER’S COSTS

Where an acquisition/procurement project has included the Codification Contract Clause, there will be no cost to the Main Equipment Supplier/Manufacturer for the provision of codification related technical documentation/drawings and/or draft item identification. The costs of the provision of Technical Documentation/drawings and/or Draft Item Identification shall be included in the contract under the sub-clauses set out in the Codification Contract Clause. It is the responsibility of the Main Equipment Supplier/manufacturer to ensure that all sub-contractors are aware of the requirement for supporting Technical Documentation /drawings and/or Draft Item Identification and to include the Codification Contract Clause in any contract let to a sub-contractor. The cost of the actual codification is the responsibility of the Government Defence Entity Acquiring/Procuring the equipment in question.

[Top]